Phase 1 • QP Network

Building the first operational journey from collection to respectful final placement.

Phase 1 is the planned foundation that connects Qur’an collection, secure storage, inspection, pilot validation, scalable processing and permanent respectful placement through one documented chain of custody.

Phase 1 brings collection, secure storage, pilot validation and processing preparation into one documented programme.
Phase 1 Scope

What Phase 1 is designed to establish

Phase 1 combines the technical project scope and financial plan so visitors can clearly see what the programme covers and where voluntary support is directed.

01

Collection network

Respectful handover through Collection Points, pickup routes and controlled packing.

02

Secure storage & inspection

Segregated receiving, Q1–Q5 inspection, records, quarantine and safe temporary storage.

03

100 kg/day validation pilot

The 100 kg/day pilot measures fibre size, dust behaviour, bulk density, biodegradation and material flow as the basis for the processing system.

04

1 TPD processing foundation

Planned 3–8 mm dry-fibre system with 12 operating and 2 reserve reusable cells.

05

Permanent respectful placement

Processed material is not released for agriculture or commercial reuse; it moves only to the approved Sacred Repository route.

Batch B1 Picture 17 — Warehouse — male volunteers
Design Basis

Base design at a glance

The current Phase 1 design basis is summarised below.

1,000 kg/daynominal daily capacity
365 tonnes/yearannual design capacity
7 tonnes/weekweekly batch
12 + 2operating + reserve cells
~72 m³working volume per cell
14–15 weeksbase biological processing period
1–1.5 acresplant land, excluding the Sacred Repository
3–8 mmtarget irregular fibre size
Financial Model

Phase 1 financial planning base

The figures below are planning estimates drawn from the project report and financial model. Final costs will reflect pilot results, vendor quotations and actual site conditions.

₹4.225 crorebase plant CAPEX
₹0.30 croreinitial working capital
₹4.525 croreinitial plant funding need
₹1.1025 croreYear-1 model OPEX at 70% utilisation
₹9.2 lakh/monthaverage Year-1 operating funding need
₹0.9–1.5 crore/yearproject-report full-capacity OPEX range
Land purchase, the Permanent Sacred Repository and the statewide collection network are separate funding components and are not included in the base plant funding figure shown above.
Batch D2 Picture 40 — Phase-1 facility/infrastructure planning
Phase 1 Public Support

Sponsor the Journey of Qur’an Preservation

Support the public-service journey, not a disposal fee.

Voluntary support can help collection, transport, secure storage, inspection, pilot testing, safety systems, processing infrastructure, QR traceability and permanent respectful placement. A contribution is never a condition for handing over Qur’anic material.